Sr. No. |
Description and Address |
Name of the Client |
Order No. & Date |
|
|
|
|
1 |
Unloading, Leading, Shifting, Fitment, Alignment, Welding, Erection & Fabrication of Equipments at Baraya - Gujarat |
Ashapura Volclay - Bhuj Gujarat |
AML/BAR/CER/HK/03-B/2014-2015 |
2 |
Annual Overhualing of Boiler of CPP Plant |
M/s.Finolex Industries Ltd. |
FIL/CPP/SER/BLR/14448/009/2013/SD |
3 |
Dismantling , Erection & Commssioning of vortex Core Pipe & Core Ring |
M/s.a2z Maintenance & Engineering Services |
A2Z/MES/13-14/05 Dated:05.03.2014 |
4 |
Dismantling, Erection, fabrication, & Restoration of heater No. 3 of CFHTM Plant |
M/s. Indorama Synthetics Pvt. Ltd |
4093011717 Dated: 26.11.2012 |
5 |
Fabrication ,Erection of 147 KL Tank, at Bharuch, Gujarat |
M/s. NOCIL Ltd |
D/D/PON/2013/05/77 Dated : 10.05.2013 |
6 |
Hot water generator . Erection, Testing and commissioning of 1 No. of 30 TPH hot water generator ( Deareator) at Meerut, U.P. |
M/s. Continental Tyres |
4500184998 |
7 |
Erection & Commissioning of existing old 15TPH Oil Fired boiler . |
M/s. Grace industries |
GIL/CPP/LOI/12-13/04 Dated:26.06.2012 |
8 |
Unloading, Fabrication ,Erection & Alignment job 2 X35 MW Power Plant |
M/s. Top Worth Private Ltd. |
TIPL/LE/1007/01 Dated: 20th June, 2011 |
9 |
Erection and commissioning of 70 TPH CFBC Boiler. |
M/s. Prithvi Ferro Alloys Pvt. Ltd, |
PO/PFAPL/GGN/11/2 Dated : 27.01.2011 |
10 |
Erection, Testing & commissioning of 1 No. of 230 TPH, CFBC Boiler and its auxiliaries for 1 x 50MW Power Projects, Ratija, Korba Dist. Chhattisgarh. |
M/s. Spectrum Coal & Power Ltd. |
SCPL/LEPL/HPG/10-11 Date : 23.08.2010 |
11 |
Erection and commissioning of 75 TPH, CFBC Boiler for our 1 x 15 M.W Cogen based power plant project at Fazilka in Punjab. |
M/s. a2z Powercom Pvt. Ltd |
a2z PPL/10-11/Fazilka/WO-007 Dated : 18.05.2010. |
12 |
Erection and commissioning of 75 TPH, CFBC Boiler for our 1 x 15 M.W Cogen based power plant project at Fazilka in Punjab. |
M/s. a2z Powercom Pvt. Ltd |
a2z PPL/10-11/Fazilka/WO-007 Dated :18.05.2010. |
13 |
Service charges towards Non destructive testing, visioning for IBR approvals, IBR documentation & Supervision of 1 x 250 TPH CFBC Boiler of wuxi Huaguang, china make for 61.5 M.W Thermal Power Project of Abhijeet Infra. Ltd, at Mihan, Village : Nagpur |
M/s. D.F. Power Systems Pvt. Ltd, |
AINL/BOIL/S/09/0476&0475 Dated : 18.03.2010. (Unit IV) |
14 |
Service charges towards Non destructive testing, visioning for IBR approvals, IBR documentation & Supervision of 1 x 250 TPH CFBC Boiler of wuxi Huaguang, china make for 61.5 M.W Thermal Power Project of Abhijeet Infra.Ltd, at Mihan, Village : |
M/s. D.F. Power Systems Pvt. Ltd, |
AINL/BOIL/S/09/0363 & 0362 Dated. 22.01.2010.(Unit III) |
15 |
Erection of Boiler including piping, testing and commissioning (Capacity - 110 TPH at 110 |
M/s. Finolex Industries Ltd, |
FIL/CPP/CVL/RS/0102/2009 Dated. 14.07.2009. |